Installation & Commisioning
The commissioning procedure guarantees you a secure UPS operation from the very start.

If you have opted for a UPS solution from GUTOR, we will support you from the award of the order onwards. Through the design, production, acceptance, delivery, through the installation, up to and including the reliable commissioning.

The commissioning is a component part of a correct installation. It guarantees you compliance with the guarantee conditions and secures you an optimised operation according to the GUTOR specifications. The UPS system thereby has a longer service life and its availability will be maximised.

Important points
  • Electrical installation must be completed before carrying out the commissioning
  • Calculate approx. 4 weeks  run-up time for this service
  • Speak to our employees about installation support
  • The installation is not included in this service
Information
  • The GUTOR factory guarantee will become invalid if there are defects in in the UPS installation  due to incorrect installation by non-authorised personnel

Services included in the commissioning programme from GUTOR
Ensuring the correct installation, parameterisation and functionality of the UPS operation according to the GUTOR specification
  • Visual inspection of the UPS area
  • Visual inspection of the UPS system and the batteries for faults and damage
  • Compliance with the installation conditions
  • Aeration and de-aeration, air conditioning of the UPS system and the battery compartment
  • Compliance with the GUTOR basic conditions according to the GUTOR specification

Checking the installation

  • Inspection of all UPS power and control wiring connections.
  • Inspection of all battery connections
  • Compliance with the local standards and safety regulations.
  • Dimensioning of the protective equipment.
  • Neutral line and star-point handling

Measurements and tests
  • Checking the power and control connections
  • Carrying out a comprehensive diagnosis and self-test, in addition to checking the switching sequences

Communication interfaces
  • Checking the communication boards and links
  • Setting up the Tele-service (optional)

Battery test
  • Checking the battery capacity and the compliance with the regulations for the layout of the battery.
  • Check of the technical features, discharge test

Instruction
  • Instruction in the operation of the UPS system
  • Transfer of know-how regarding UPS circuit handling or the handling in case of mains power loss

Customer advantages from the GUTOR commissioning

  • Security and continuity of your GUTOR Guarantee and guarantee extension
  • Implementation by GUTOR trained and certified specialist personnel of the manufacturer
  • GUTOR coordination and clear allocation of responsibilities for a smooth implementation
  • Complete inspection, test and parameterisation of the UPS system for optimum performance and service life
  • Documentation of all components, settings and environmental conditions on-site in a comprehensive report
  • Central storage of the system data and history for a fast reaction to questions regarding retrofitting and conversions, service deployments or fault analyses
  • Start of the factory guarantee with the execution of the commissioning, instead of the delivery date
 